Sub-Floor Finished
This week was all about flooring. Structural flooring that is. The architectural, aesthetically pleasing portion of flooring is still a […]
Read more →Homesteading in the Suburbs
This week was all about flooring. Structural flooring that is. The architectural, aesthetically pleasing portion of flooring is still a […]
Read more →I had hoped that I could I have titled this post “Last Beam and Floor Construction Finished” but alas the […]
Read more →The joinery continued on this week with the tie beams and plate beams. We also managed to do some rafters […]
Read more →We finished up the posts this week and moved on the first of the beams. I thought the 8×8 posts […]
Read more →The lumber for our timber frame was delivered last week before we poured the piers. My friend John came out […]
Read more →This week we did the form work and poured the concrete pier foundation. I cleaned out the holes we dug […]
Read more →We finally broke ground on the timber frame cabin this week. This is the first hole of total of nine […]
Read more →I’m planning on using a raised floor, pier and beam foundation. Most houses in my area are on a single […]
Read more →I’ll be using 4×10 rough sawn timbers for the rafters. The roof deck will be 2×6 tongue and groove cedar […]
Read more →I requested estimates for the timbers and 2×6 tongue and groove decking from Ryan Wholesale and McCoys. I also requested an […]
Read more →