T-Brick Shed: First Course
Laying out the forms for the first course. We have five 12″X12″ forms and one 18″X12″ form. Forms are all […]
Read more →Homesteading in the Suburbs
Laying out the forms for the first course. We have five 12″X12″ forms and one 18″X12″ form. Forms are all […]
Read more →I took the weekend off from the T-brick shed because: A) I wanted to give the footer/grade beam a little […]
Read more →Dad finished up the forms earlier in the week so we were able pour the footer today. A footer is […]
Read more →The last load of gravel for a grand total of five cubic yards. There are 27 cubic feet in a […]
Read more →This is what I did during the part of the weekend I wasn’t shoveling gravel. Looks like fun huh? Removing […]
Read more →Finished up the installation of the french drain and went through two and a half cubic yards of gravel today. […]
Read more →The last thing Jean told me before she left for the UK was that I had better finish the shed […]
Read more →I had planned on starting installation of the french drain and rubble trench foundation today but unfortunately/fortunately it rained earlier […]
Read more →The Mattock We spend part of the Labor day weekend leveling and widening the foundation trench. I bought a Mattock […]
Read more →The plan is to put in a rubble trench foundation. A rubble trench is a trench filled with rubble or […]
Read more →